Short answer: When a planned maintenance shutdown begins at a chemical plant or a major-hazard (Seveso-type, known in Turkey as BEKRA) establishment in Kocaeli, the main job of the security team at the gate is to make the permit-to-work system visible at the gate. In practice that means letting in only contractor personnel the operator has approved, for the days and areas they are approved for, and only once their site induction is complete; being able to say at any moment who is on site; and handing that picture over in full at every shift change. Security officers do not issue permits, test for gas or isolate equipment; those tasks belong to the operator's process and occupational safety teams. What security adds is making sure the permit system and the gate list run on the same information, updated at the same time.
Why does this matter so much in Kocaeli?
Kocaeli has a dense concentration of establishments that hold hazardous substances. The Kocaeli 2022 Provincial Environmental Status Report, drawing on notifications to the Ministry of Environment, Urbanisation and Climate Change's BEKRA notification system, records 57 upper-tier and 34 lower-tier establishments in the province in 2022, 91 in total. These figures should be read with care: they rest on notifications, they change from year to year, so other years may show different numbers. Even so, they give a clear sense of how concentrated this kind of site is in the province. The same report notes that the operator of an upper-tier establishment must prepare an internal emergency plan, keep it on site and upload it to the system.
Employment data point the same way. According to the Social Security Institution (SGK) Statistical Yearbook 2025, Kocaeli has 428 workplaces and 13,157 insured employees in the manufacture of chemicals. Measured against the national picture, the sector's share of compulsory insured employment in Kocaeli is about 3.3 times the Turkish average (our calculation), and only Istanbul has more insured employees in the sector. Coke and refined petroleum products employ a further 2,686, and chemicals, petroleum products, pharmaceuticals and rubber and plastics together reach about 40,765 insured employees (our total).
Continuously operating process plants usually carry out their heavy maintenance in planned shutdowns, or turnarounds. During those days the site population changes quickly: several contractor firms arrive at once, traffic in cranes, welding sets and tankers rises, and working hours stretch. A gate routine that runs smoothly on an ordinary day comes under the greatest strain at exactly this point.
Why is maintenance a distinct risk period? What the research says
The link between maintenance and major accidents has been studied in process safety for decades. In a paper presented at the IChemE Hazards XIV symposium, Iliffe, Chung and Kletz (1998) of Loughborough University (a paper of the same title appeared in Process Safety and Environmental Protection in 1999) cite the UK Health and Safety Executive (HSE) as finding that 30% of accidents in the chemical industry are maintenance-related. A quick check the authors made of the IChemE accident database found more than 700 of the 5,000 listed accidents to be maintenance-related, most of them arising not from the work itself but from errors in how equipment was prepared for maintenance or handed over. The paper also describes a familiar practical problem: because authorised issuers are hard to find when needed, permits are often issued at a set time in the morning while the work starts hours or even days later. The study reflects 1990s Britain; its value today lies in the nature of the problem rather than the numbers.
Okoh and Haugen (2013), of the Norwegian University of Science and Technology, reviewed investigation reports and earlier literature on selected major accidents in the oil, gas and chemical industries to classify how maintenance contributed. Maintenance does not only weaken barriers; it can bring new hazards on to a site, such as an ignition source, or directly initiate an accident sequence. Among planning deficiencies the authors give poor communication between maintenance and operations staff as an example, and deficient checking and supervision appear as a separate category. The study is qualitative and based on a small number of cases, but the classification is a useful lens for shutdown planning.
In a case study at a chemical plant in Iran, Jahangiri and colleagues (2016) examined the 11 main tasks of a permit-to-work process using hierarchical task analysis and the SPAR-H method. They estimated a mean human error probability of 0.11 across the process, with the highest value, about 0.51, for flammable gas testing. The authors recommend clearly defined roles and responsibilities, assigning gas testing to a separate qualified person, and automating permit issue. The findings come from a single plant and an estimation method, so they should not be generalised lightly.
The HSE's guidance page on permit-to-work systems reaches the same point: a permit is a means of communication between site management, plant supervisors, operators and those doing the work, and issuing a permit does not by itself make a job safe. Work that cannot be finished in one shift should be left in a safe state with clear instructions for the next shift, and it should be clear who is in charge of what, with no gaps or overlaps.
The lesson we draw from these sources is that the problem may be not only a missing rule but also information scattered across different places. When the gate list, the permit board and the shift log are kept without reference to one another, there is no single, current answer to the question of who is where, doing what.
How can gate control and the permit system work together?
Before the shutdown: one source, one list
- Pre-qualifying and approving contractor firms is the operator's job. The security team works from the list that flows from that approval: firm, individual, work area, valid dates and whether site induction is complete.
- The gate list is fed from the same source as the permit system. If a separate spreadsheet is kept, it is agreed in writing which record governs and how often a day the two are reconciled.
- Vehicle and equipment movements such as cranes, tankers and welding sets are logged separately from people, with the gate, the hours and the escort agreed in advance.
- Rules on mobile phones, lighters and other ignition sources are set by the operator's process safety team; security agrees with the operator, in writing, how they will be applied at the gate.
- Temporary passes show the area and the dates; an expired pass either fails at the gate or is easy to spot.
During the shutdown: who is on site?
- Gate records should be built into the muster and head-count arrangements of the internal emergency plan. When an alarm sounds, the number of contractor personnel on site and their firms should be available within minutes.
- Anyone not on the list, whose entry approval has expired or whose induction record is missing is turned away and the case reported to the person the operator has named; there is no negotiating at the gate.
- Patrols watch for and report unauthorised entry into restricted areas the operator has marked; they do not touch isolated or locked-out equipment.
- Exits are recorded too. Anyone logged in but not out by the end of the day is raised with the operator as an open question.
Shift change and handover
During a shutdown the most fragile moment is the shift change. The permit handover and the security shift handover should carry the same information: open permits, firms and head counts on site, entries refused during the day and questions still pending. The simplest way to achieve this is to include a current summary from the permit system on the gate handover form.
When the shutdown ends
Temporary passes are collected, contractor lists are closed, records are kept for the period the operator sets, and the operator receives a short summary: how many firms, how many entries, how many refusals and where things went wrong. That summary is the most concrete input to planning the next shutdown.
| Stage | Permit-to-work system (operator) | Gate and security team |
|---|---|---|
| Preparation | Contractor approval, permits, site induction | Take the approved list from the same source; plan passes and vehicle entry |
| Entry | Scope, area and duration of each permit | Check the list and induction record; turn away and report any mismatch |
| Work | Gas testing, isolation, job supervision | Keep the on-site head count current; watch restricted areas |
| Shift handover | Handover of open permits | Gate handover using the same summary |
| Close-out | Permits closed | Collect passes, match exits to entries, report a summary |
Common mistakes
- Keeping the gate list in a hand-updated spreadsheet separate from the permit system, with no one sure when the two were last reconciled.
- Approving a contractor firm but not checking, one by one, the people it brings on site.
- Relaxing checks to clear the queue on the first morning of the shutdown.
- Logging vehicles and equipment in the same record as people, or not logging them at all.
- Expecting security officers to carry out specialist tasks such as gas testing or isolation checks.
- Handing over the gate at shift change by word of mouth only.
- Leaving temporary passes uncollected and contractor lists open after the shutdown.
Notes for operating in Turkey
The duties of major-hazard establishments are set by Turkey's Regulation on the Prevention and Mitigation of Major Industrial Accidents, which covers notification and the internal emergency plan. Law No. 6331 on Occupational Health and Safety requires employers who share a workplace to cooperate and coordinate on health and safety; in practice, contractor management and the permit system sit within the operator's occupational health and safety organisation. A private security officer's powers are listed in Article 7 of Law No. 5188; at the gate the officer applies the entry rules the operator has set and checks the list, but does not issue or approve permits. Contractor lists, pass logs and camera images identify individuals, so Law No. 6698 on personal data applies: tell contractor personnel what is recorded and why, and agree with the operator when the shutdown records will be deleted. How we set up security at sites that handle hazardous substances is explained on our critical infrastructure security page.
Titan Savunma is an Ankara-based private security company licensed by the Ministry of Interior under Law No. 5188 and certified to ISO 9001, 14001, 45001, 22301 and 28000. We work with international companies in English and Turkish, and our Kocaeli City Manager, supported by our Marmara Regional Directorate based in Bursa and our Istanbul General Directorate, works with your process safety team to turn the gate list into an entry, head-count and handover routine that runs on the same information as your permit system; see our page on private security in Kocaeli. To discuss your site, please use our contact page.
Sources and Further Reading
- T.C. Kocaeli Valiliği Çevre, Şehircilik ve İklim Değişikliği İl Müdürlüğü — Kocaeli İli 2022 Yılı Çevre Durum Raporu, Bölüm Ç: Büyük Endüstriyel Kazaların Önlenmesi Çalışmaları, Çizelge Ç.49 (2023)
- Sosyal Güvenlik Kurumu — SGK İstatistik Yıllığı 2025, Sigortalı ve İş Yeri İstatistikleri (Tablo 1.11)
- Health and Safety Executive (UK) — Human factors: Why are permit to work systems important?
- Iliffe, R.E., Chung, P.W.H. & Kletz, T.A. — More Effective Permit-to-Work Systems, IChemE Symposium Series No. 144 (Hazards XIV), Institution of Chemical Engineers (1998); dergi sürümü: Process Safety and Environmental Protection 77(2):69–76 (1999), DOI 10.1205/095758299529839
- Okoh, P. & Haugen, S. — The Influence of Maintenance on Some Selected Major Accidents, Chemical Engineering Transactions 31:493–498 (2013)
- Jahangiri, M., Hoboubi, N., Rostamabadi, A., Keshavarzi, S. & Hosseini, A.A. — Human Error Analysis in a Permit to Work System: A Case Study in a Chemical Plant, Safety and Health at Work 7(1):6–11 (2016)