This article is general information, not legal advice.
A planned shutdown or turnaround changes a plant's security picture overnight. For a few days or weeks, a site that normally sees familiar shift crews receives large numbers of contractor workers, cranes, scaffolding, tool containers and delivery trucks, often around the clock. Gates designed for routine traffic face queues, normal zone boundaries are opened for maintenance, and valuable materials such as cable, catalyst, spare parts and tools sit in temporary laydown areas.
The security task during a turnaround is to keep the site controlled without slowing the work: register and induct every person, move people and vehicles through the gate at the rate the schedule needs, control tools and materials in both directions, support (not replace) the permit-to-work system, and close everything down cleanly at the end. Below is a checklist that a plant manager or turnaround manager in Turkey can use with the security provider, with the Turkish occupational health and safety rules that frame it.
1. Planning: start with the turnaround schedule
Security planning should run on the same timeline as the turnaround plan, not begin in the last week. The main inputs are the contractor list, expected peak headcount by day and shift, crane and heavy-vehicle movements, laydown locations and the areas that will be opened.
- Name one security lead who sits in turnaround coordination meetings and reports to the turnaround manager.
- Agree roles in writing: the plant owns permits and OHS coordination, each contractor owns its people, and security owns gate control, registration checks, patrols and the incident log.
- Decide staffing per post from the shift pattern, opening hours and legal working-time limits. Staffing is planned per site and per phase; there is no universal number.
- Prepare a separate plan for mobilisation, peak and demobilisation, because each phase stresses different controls.
2. Contractor registration and induction
Turkish law puts the induction question on a firm footing. Under Article 16(2)(b) of Occupational Health and Safety Law No. 6331, the host employer must give the employers of workers coming from other workplaces the information those workers need about site risks, protective measures and emergency arrangements. Article 17(5) goes further for workplaces classified as hazardous or very hazardous: workers coming from other workplaces may not start work without a document showing they have received training with adequate information and instructions on the health and safety risks of the work. Article 23 requires employers sharing the same work area to cooperate, coordinate risk prevention and inform each other.
Security does not deliver OHS training, but it is the control point that makes those rules real at the gate:
- Contractors submit worker lists in advance through a single channel; no names are added verbally at the gate.
- A temporary pass is issued only after identity is checked against the list and the induction record is confirmed.
- Passes show the contractor's name, a validity date and the zones the holder may enter, so that anyone out of place is easy to spot.
- Collect only the personal data needed for access and safety, explain it in a privacy notice, and set a deletion date after demobilisation, in line with the Personal Data Protection Law No. 6698.
3. Gate throughput and vehicle control
The most common failure in a turnaround is not intrusion but a gate that cannot keep up, so checks are skipped at shift change. Design for the peak:
- Separate pedestrian and vehicle lanes, and if possible a dedicated contractor gate away from the product dispatch gate.
- Stagger contractor start times with the turnaround manager to flatten the morning peak.
- Pre-book heavy deliveries and crane arrivals into time slots, with a holding area outside the gate.
- Keep private cars of contractor workers outside the process area wherever possible; use buses from a car park.
- Escort or route-control vehicles entering live areas, coordinated with the plant's internal traffic plan.
4. Tools, scaffolding and materials
Turnarounds move high-value, portable items in both directions. The twenty-five techniques of situational crime prevention developed by Cornish and Clarke, published by Arizona State University's Center for Problem-Oriented Policing, give a useful vocabulary: control access to facilities, screen exits, identify property, set rules and post instructions. Applied to a turnaround:
- Identify property: contractors declare their tool containers and major tools on entry; plant-owned spares and materials are tagged.
- Screen exits: anything leaving the site needs a material exit note signed by a named plant person; security checks the vehicle against the note.
- Control access: laydown areas and temporary stores are fenced or at least lit and patrolled, with a key or access log.
- Set rules and post instructions: clear signage on photography, smoking, phones in classified areas and prohibited items, in Turkish and, where needed, other languages used by the workforce.
- Scrap and removed equipment: removed insulation, cable, metal and catalyst follow a documented route to a controlled area and leave only with paperwork.
5. The permit-to-work interface
Permit-to-work belongs to operations and OHS. In Turkey, for example, where an explosion protection document requires it, work in hazardous areas must follow written instructions and a work permit system, with the permit issued in writing by an authorised person before work starts; the Ministry of Labour's 2021 programmed inspection report on major-hazard workplaces lists missing work permits in potentially explosive atmospheres among the findings inspectors look for. The UK Health and Safety Executive's technical guidance on permit-to-work systems names as major hazards both unauthorised staff performing permit functions and failure to hand plant back in a safe condition.
Security supports that system without taking it over:
- Patrols carry a simple map of where permits are live and report hot work, confined-space entries or barriers that do not match.
- Security does not issue, extend or close permits, and does not give technical instructions.
- Any observation is reported to the permit issuer or area authority through an agreed channel, and logged.
- At night, when supervision is thinner, patrol reports are part of the morning handover.
6. Emergency readiness at peak headcount
- Muster lists must be accurate when headcount is several times normal. Gate registration is the source; reconcile it at every shift change.
- Emergency routes must stay clear of scaffolding, containers and parked vehicles; patrols check them.
- Agree how security will guide ambulances and fire services through a crowded site.
7. Close-out and access revocation
- Temporary passes expire automatically on the contract end date; collect physical cards at the last exit.
- Contractors remove their tools against the entry declaration; disputes are resolved before trucks leave.
- Laydown areas are walked and cleared, temporary gates and fence openings are closed, and normal zone boundaries are restored.
- Registration data is deleted or archived according to the retention rule set at the start.
- A short lessons-learned meeting records what slowed the gate, what went missing and what to change next time.
Quick checklist
| Phase | Security checks |
|---|---|
| Planning | Named security lead, written role split, phase plans, staffing per post |
| Mobilisation | Advance worker lists, induction confirmed before pass, zone-coded passes |
| Peak | Separate lanes, staggered starts, booked deliveries, tool declarations |
| Throughout | Material exit notes, laydown control, permit observations logged, muster lists reconciled |
| Close-out | Passes expired, tools reconciled, openings closed, data retention applied, lessons learned |
Working with Titan Savunma
Titan Savunma is an Ankara-based private security company operating under a Ministry of Interior licence granted under Law No. 5188, with ISO 9001, 14001, 45001, 22301 and 28000 certificates. We plan temporary security for maintenance periods alongside routine guarding, in English and Turkish, with a single point of contact, a written scope and regular reporting. See our pages on industrial facility security and factory security.
Sources and Further Reading
- Republic of Türkiye — Occupational Health and Safety Law No. 6331 (mevzuat.gov.tr)
- UK Health and Safety Executive — Technical Measures Document: Permit to Work Systems (COMAH)
- Center for Problem-Oriented Policing, Arizona State University — Twenty-Five Techniques of Situational Prevention (after Cornish & Clarke, 2003)
- T.C. Çalışma ve Sosyal Güvenlik Bakanlığı Rehberlik ve Teftiş Başkanlığı — 2021 Büyük Endüstriyel Kazalar programlı teftişi genel değerlendirme raporu (2022)