For a foreign EPC contractor building a power plant, transmission line, industrial facility or infrastructure project in Turkey, site security is a set of decisions that have to be made before the first container arrives: who employs the security officers, who applies for the private security permit, how the security plan connects to occupational health and safety (OHS) coordination, and how responsibility passes to the owner when the project ends. This article works through those questions phase by phase.
The short answer: if licensed private security officers will work on the site, a private security permit is needed from the provincial governorship (valilik) under Law No. 5188 on Private Security Services. The security plan should be revised for mobilisation, peak construction, commissioning and handover. And the OHS duty to keep unauthorised people off the construction site overlaps directly with what the security team does every day.
This article is general information, not legal advice.
Who holds the permit: the EPC contractor or the owner?
Under Article 3 of Law No. 5188, having security provided by a private security company requires the governor's permission, given on the decision of the provincial private security commission (özel güvenlik komisyonu). The permit is issued to the person or organisation requesting the service. Under Article 8 of the implementing regulation (Uygulama Yönetmeliği), the application states the subject of the service, how it will be delivered, the maximum number of personnel and any weapons and equipment needed. The commission sets the maximum staffing and weapons.
A common gap in EPC contracts is a clause saying security is "the contractor's responsibility" without saying in whose name the permit application is made. Article 19 of the Law makes it an offence to employ private security officers without the permit, so the applicant, the site boundary and the duration should be written into the contract. The security company must also notify the governorship in writing of each new service by the end of business hours on the day the service begins (Article 5).
- Applicant: the landowner or operator, the EPC contractor, or a joint venture?
- Permitted area: main site, laydown yards, worker camp, access roads.
- Duration and phases: construction, commissioning, post-handover transition.
The protection and security plan as a living document
Article 12 of the implementing regulation, as amended in July 2024, requires the security company to prepare a protection and security plan (koruma ve güvenlik planı) for each site within thirty days of the service starting, and to keep a current copy ready for the governorship or for inspections. On a construction site, "current" is the hard part, because the site changes every month.
| Phase | Typical risks | Plan focus |
|---|---|---|
| Mobilisation | Unclear boundaries, temporary fencing, fast-growing traffic | Permit application, main gate, ID and vehicle registration |
| Peak construction | Many subcontractors, material and fuel loss, camp life | Subcontractor access lists, material receipt and exit checks |
| Commissioning | Energised equipment, valuable spares, test teams | Restricted areas, alignment with permit-to-work |
| Handover | Responsibility gaps, stale access rights | Record transfer, ending the permit, owner's new regime |
There is no single staffing formula. Numbers depend on the shift pattern, operating hours, legal working-time limits and the size of the site. They are planned for each phase and stay within the maximum the commission has approved.
Material and fuel loss
Cable, copper, rebar, small tools and generator fuel are the items most often lost on construction sites. The security team's role is not to run the store but to match paperwork against what physically leaves at control points. Article 16 of Law No. 5188 states that private security personnel may not be employed in work other than protection and security services. Stock counts and fuel issuing therefore stay with the materials team.
- Material leaves the site only with a signed exit form and a recorded vehicle plate.
- Fuel tanks and dispensing points have recorded, limited access and camera coverage.
- Weekly reconciliation: the materials team's stock report is compared with security exit records.
We cover this topic in more depth in our bulletin on construction material and fuel security.
Subcontractor access and worker camps
At peak, a large project can have dozens of subcontractors and workers of many nationalities. Access control starts with each subcontractor submitting a current worker list together with OHS induction records, and removing leavers on the day they leave. Badges should show the permitted areas and the validity period.
A worker camp is a place where people live. A private security officer's powers are limited to those listed in Article 7 of Law No. 5188, and Article 9 restricts them to the duty area and duty hours. Camp rules and discipline stay with the employer. The security team focuses on entry and exit, visitors and emergency arrangements. Identity and visitor records kept at the camp are personal data under Turkey's data protection law (KVKK), so retention periods and access rights should be set in advance.
The OHS interface: two legal regimes, one site
Article 23 of Law No. 6331 on Occupational Health and Safety requires employers sharing the same work area to cooperate and coordinate OHS measures and to inform one another of risks. Article 22 sets rules for coordinating OHS committees where a main employer and subcontractor relationship lasts more than six months. The security company, as the employer of its officers, is part of this coordination.
Under Article 8 of the Regulation on Occupational Health and Safety in Construction Works (2013), where more than one employer or subcontractor works on the same construction site, the employer or project manager appoints a health and safety coordinator, and prepares or commissions a health and safety plan before work starts. Under Article 11, during construction the coordinator makes arrangements to keep anyone other than authorised persons from entering the site. In practice, the security team is the one carrying out that arrangement at the gate, so the OHS plan and the security plan should reference each other.
- Security officers receive the site OHS induction and personal protective equipment.
- The emergency plan fixes the muster points, ambulance access and who may open which gate.
- At areas requiring a permit-to-work, security does not admit anyone without seeing the permit.
Commissioning and handover to the owner
Handover is the most fragile period. EPC teams shrink, the owner's operations team arrives, and old access rights often remain open. Under Article 3 of Law No. 5188, a private security arrangement (other than temporary ones) may be ended by commission decision and governor approval, provided the application is made at least one month in advance. If the owner will hold its own permit, that timetable has to be planned to match the EPC contractor's exit.
- Access cards, keys and codes are handed over with an inventory, and EPC rights are closed on handover day.
- Incident records and open issues go into a written handover report.
- The parties agree which data controller keeps camera and visitor records, and for how long.
- A short overlap period lets both teams work the same shifts before the change.
Common mistakes
- Remembering the permit application only after construction has started.
- Leaving the worker camp or remote laydown yards outside the permitted area.
- Giving security officers non-security work such as storekeeping, driving or camp services.
- OHS and security plans written by separate teams that never compare notes.
- Not scheduling the end of the EPC permit and the start of the owner's permit.
For project-scale planning, see our pages on construction site security and security for international companies in Turkey.
About Titan Savunma
Titan Savunma is an Ankara-based private security company operating under a Ministry of Interior licence issued under Law No. 5188. It holds ISO 9001, 14001, 45001, 22301 and 28000 certificates, works with international companies in English and Turkish, and plans services for sites in different provinces of Turkey with a single point of contact, written scope and regular reporting. Learn more on our private security in Turkey page.
Sources and Further Reading
- Law No. 5188 on Private Security Services, Mevzuat Bilgi Sistemi
- Özel Güvenlik Hizmetlerine Dair Kanunun Uygulanmasına İlişkin Yönetmelik (current consolidated text), Mevzuat Bilgi Sistemi
- Law No. 6331 on Occupational Health and Safety, Mevzuat Bilgi Sistemi
- Yapı İşlerinde İş Sağlığı ve Güvenliği Yönetmeliği, Resmî Gazete 5 October 2013 No. 28786