This article is general information, not legal advice.
Building a data centre in Turkey looks like any large construction project from the road: hoardings, cranes, a gate and a site office. The security problem inside is different. Expensive electrical and cooling plant arrives in a tight sequence, and a delayed or damaged generator, transformer or switchboard can move the whole programme. The drawings describe exactly where power, cooling and network routes run, which makes them sensitive long before the first server arrives. And on many projects part of the building goes live while construction continues next door, so a construction workforce shares a site with a facility that must already meet operational security standards.
A sound plan therefore covers six things: receipt and storage of high-value equipment, confidentiality of design information, a firm boundary between live and construction areas, contractor vetting and induction, controlled access during commissioning, and a clean handover to the operations security team. This guide takes them in order, at planning level.
Why mission-critical construction needs its own plan
Ordinary site security focuses on theft of tools, materials and fuel, and on keeping the public out of a hazardous area. Those risks still exist, but on a data centre project the consequences of a single loss or act of tampering are larger, and the number of parties is high: general contractor, mechanical and electrical subcontractors, equipment vendors, commissioning agents, the future operator and often the tenant's own engineers.
The design principles are the same ones used on any well-run site. In their review of crime prevention through environmental design (CPTED) published in Property Management, Cozens, Saville and Hillier describe territoriality, surveillance, access control, maintenance, activity support and target hardening as the core principles. They also note honestly that the evidence base is criticised and not conclusive, while judging CPTED a pragmatic tool. That is the right attitude for a construction site: use the principles to lay out the gate, the laydown yard and the site office so that people and vehicles are naturally seen and channelled, and then measure what actually happens.
High-value equipment: receipt and storage
Most losses and disputes on mission-critical projects happen at the boundary between the logistics chain and the site. The control catalogue in NIST's SP 800-53 Rev. 5 contains a short control, PE-16 Delivery and Removal, that captures the principle well: authorise and control the components entering and leaving the facility, keep records of them, and where necessary restrict delivery areas and isolate them from the system areas. On a construction site this translates into:
- a delivery schedule shared with the gate, so that every arrival is expected and named;
- verification of vehicle, driver and documents against the schedule before the gate opens;
- inspection of packaging and seals at receipt, with photographs taken by an authorised person and differences recorded on the delivery note;
- a defined laydown or storage area for each equipment class, with access limited to named people and a record of every movement in and out;
- a rule that equipment leaving the site, including returns to the vendor, needs the same written authorisation as equipment arriving.
Movement routes and timings are sensitive and should stay in a limited-distribution document, not on a notice board.
Design confidentiality and photography
A data centre's drawings, cable routes, single-line diagrams and security system layouts tell a reader where the facility is weakest. ISO 19650-5, the security-minded part of the international building information management series, addresses exactly this. Its published scope says it specifies principles and requirements for security-minded information management, aims to build a proportionate security mindset and culture, and applies across the lifecycle of a project or asset. For the site team that means:
- a written decision on which information is sensitive and who may hold it;
- controlled printing and collection of drawings in the site office, with sensitive sets returned at the end of each day;
- a photography rule: no photographs of security systems, cable routes or plant rooms except by named people for documented purposes, and no posting of site photographs on social media without approval;
- hoarding and gate layouts that do not expose plant areas to view from the street;
- removal of company and project names from signage where the client wishes to keep the facility low-profile.
Camera systems on site also record workers. Under Turkey's Personal Data Protection Law (KVKK, Law No. 6698) the controller must tell people about recording and keep footage only as long as the purpose requires, so camera notices and retention periods belong in the site plan from day one.
Phased handover: the live and construction boundary
When a first data hall goes live while later halls are built, the site holds two security regimes. The live area must meet the protection classes the facility is designed to, for example under EN 50600-2-5, whose public preview shows that protection classes are assigned to every space and supply path. The construction area runs under the contractor's site rules. The boundary between them is the most important line on the drawings.
- Give the live area its own entrance and route, never through the construction zone.
- Make the boundary physical: full-height partitions, locked doors with alarms, and a single controlled crossing point for the few people who must work on both sides.
- Issue construction credentials that do not open live-area doors, and review the crossing list weekly with the operator.
- Coordinate hot works, dust-producing work and power shutdowns with the operator through the permit-to-work system.
- Protect shared supply paths, such as cable routes and pipework passing through construction zones.
Turkish occupational health and safety law also requires coordination here. Article 23 of Law No. 6331 requires employers sharing the same working area to cooperate on safety measures, coordinate prevention work and inform one another of the risks. The operator, the main contractor and the security provider should therefore agree one coordination meeting and one incident reporting route.
Contractor vetting and induction
Peak construction brings many workers through the gate, often from several subcontractors at once. Under Law No. 6331, employers must inform employees about the health and safety risks of the workplace (Article 16) and ensure they receive training before starting work (Article 17). A short security induction fits naturally into that training: what may and may not be photographed, how to report lost credentials, where workers may go, and what to do if they see someone in the wrong area.
Vetting should be proportionate. Confirm identity and employer, link each credential to a named subcontractor and an end date, and collect only the personal data that has a clear purpose and legal basis. The credential should expire automatically when the subcontract ends or the worker leaves, and the subcontractor should be obliged in the contract to notify departures the same day.
Commissioning: the riskiest weeks
Integrated systems testing is when the building is most valuable and least protected. Vendors' engineers arrive for short visits, doors may be held open for cable pulls, access control may still be in test mode and alarms may be suppressed while systems are tuned. Plan compensating measures for exactly this period:
- a commissioning access list approved by the commissioning manager and the future operator;
- temporary credentials with short validity, or escorted access where the access control system is not yet live;
- a log of every door or alarm placed in test or bypass mode, with an owner and a reset time;
- increased patrols or a person posted where electronic protection is temporarily missing;
- a clear escalation route so that the security team can ask the commissioning manager to stop work in an area if the agreed conditions are not met.
Handover to operations
The last step is often rushed. A good handover package includes the final access list with all construction credentials disabled, the key register reconciled and master keys recut where required, as-built security drawings delivered to a restricted file, ownership of the access control and video systems transferred to the operator, and updated post orders for the operational guarding team. Run a short joint walk-through of every boundary before signing.
In Turkey, the operational guard force will work under Law No. 5188, which makes the employment of private security staff subject to the governor's permission (Article 3). If the operator plans to use a security company after handover, start that process early so that there is no gap between the contractor's site security and the operational service. Staffing for both phases depends on the shift pattern, the number of active gates and crossings, working hours and legal limits, and is planned for each phase separately.
Working with Titan Savunma
Titan Savunma is an Ankara-based private security company licensed by the Ministry of Interior under Law No. 5188 and certified to ISO 9001, 14001, 45001, 22301 and 28000. We work with international companies in English and Turkish, and plan services for sites in different provinces with a single point of contact, a written scope and regular reporting. See our approach to construction site security, data centre physical security and critical infrastructure security.
Sources and Further Reading
- Cozens, Saville & Hillier — Crime prevention through environmental design (CPTED): a review and modern bibliography, Property Management 23(5) (2005)
- NIST — SP 800-53 Rev. 5, Security and Privacy Controls for Information Systems and Organizations (2020)
- ISO 19650-5:2020 — Security-minded approach to information management, scope (national standards store listing)
- Mevzuat Bilgi Sistemi — Law No. 6331 on Occupational Health and Safety (2012)
- CENELEC/SIST — prEN 50600-2-5 Security systems, public document preview (2020)
- Mevzuat Bilgi Sistemi — Law No. 5188 on Private Security Services (2004)